Boulevard One Construction Updates
June 25, 2014
First Avenue
Boulevard One construction activity will affect First Avenue between Monaco Parkway and Pontiac Street this summer. Traffic flow on First Avenue will be maintained throughout the work. New roads will connect to First Avenue, and the south side of First Avenue will be improved with a new sidewalk, street trees, bicycle lane and underground utilities.
Monaco Parkway
Two construction projects are underway or planned near the berm on Monaco Parkway. The Lowry Boulevard corridor is being graded to allow for installation of electrical utilities. Lowry Boulevard will not be connected to Monaco Parkway until 2016. Lowry Boulevard, from Niagara Street to Quebec Street, will be built and opened in 2015.
More information is posted under “Current News” at www.boulevardonelowry.com.